Self levelling the WC Makes the loft look bigger than it is!  Well Crocks Stage 2 Well Stage 15 - concrete apron BUSY day.  Water! Hearth in place, stove situated Picking up Some of our Ash Flooring Saturday AM. 

Welcome

Image
Shingles have finally been completed.  Happy with the entry! All shingles on! Second attempt at water.  Seems positive.   Tool unloading on a chilly November afternoon.  Frozen water at the market Elsie getting treats. 

Garage Access.

Image
Then it turned cold. Frozen Slushy rain!   The lower driveway. Potential well site.  Inspector Jean

Four Doors

Image
All four garage doors have been dry fit and need some minor adjustments.  They work well! Tiles for the bathroom.  Lucy In The Box

And a stove!

Image
How could I forget the stove?  It is there but still not attached.  

One Big Hole

Image
We showed up on Thursday expecting Plumbers but found the excavator came back.   Prepped area and dug a hole...dry. Waited...still dry. Dug deeper...dry.   Disappointing to say the least. Electrical is ready for inspection.   First garage door was dry fit and works really well!  Still no shingles. Bathroom in-floor heating Cement over-pour.   Lovely electrical work. Painting window trim ... Monster Mash at A&S's.  Washer Pan. Well prep.  D&J visit!   A nice big hole.   Door #1 looking good!  (no it will not stay that colour!).